Latest updates and progress

 

ONGOING THROUGHOUT 2017

Everards Meadows roadworks

If you have driven by Everards recently you will have seen porta cabins and diggers appearing.  It’s not the start of our new brewery, or the demolition of our current one (we’re still in here brewing!) but some preparation work for our future plans.

Everards are working with construction partner, Kier, to start some work on our new Everards Meadows site.  The work is to create an entrance and exit plus bring drainage onto the site. The work will take around 27 weeks in total and has started this week on Soar Valley Way and on the Everards Meadows site which is opposite Everards’ current home.

We know that roadworks can be challenging so have spent a lot of time liaising with Leicestershire County Council, all utility companies and Fosse so that our works here minimise disruption for everyone passing by or visiting the area.  We’ll be staggering the work and completing as much as possible at night time and we have delayed the start to avoid clashing with the Leicestershire County Council works nearby.

We’ll be updating this page fortnightly with our progress and what's coming up.

UPDATE FOR w/c 24TH aPRIL

You may have seen some signs advertising a closure on Grove Way (the road from Soar Valley Way to the Everards Way roundabout into Fosse Park South)  The road won’t be completely closed but will be only open one way, allowing traffic to flow into Fosse Park.  All other exits will be open to use as alternatives.

This closure starts on 8th May and is planned for 7 weeks.  We appreciate that this may cause some inconvenience, indeed it will for our own team and deliveries, so we will try to work as quickly as we can.

 

Update for w/c 17th April

We have completed the overnight works on Soar Valley Way (in fact this was done four days earlier than anticipated!). We are now working on the entrance onto our Everards Meadows site and during this work we are able to keep two lanes of Soar Valley Way open to keep traffic moving. 

In addition we have begun drilling to bring the drainage from near our current brewery over to the Everards Meadows site.  As we updated on 3rd April, this work continues to be on our own sites so we can minimise disruption.

Got a question?

Drop us an email to mail@everards.co.uk or call us on 0116 2014100.


December 2016

Rutland Cycling to open new store at Everards Meadows


November 2016

£150m Castle Acres Shopping Park plans recommended for approval


April 2016

Everards Meadows planning permission is granted


April 2016

Everards' new logistics centre at Optimus Point is completed


November 2015

Cycle Centre plans shared


November 2015

Everards Meadows plans shared


June 2015

Castle Acres Shopping Park plans submitted